Works taking place 

From Monday 2 May 2022 works to relocate existing combined service route (CSR) cabling will continue. 

Crews will be undertaking excavation, trenching, boring and conduit installation works adjacent to the rail corridor fence line. 

Between 7am and 6pm on Tuesday 10 May there will be a temporary road closure on Churchill Street, adjacent to Box Place to set up a crane and facilitate the delivery of large concrete pits to site. Access to driveways will be maintained for local residents with the assistance of traffic management staff upon request.

So far on Churchill Street, while working to install the new CSR components, crews have: 

  • delivered and installed33 pre-cast concrete pits 
  • completed approximately 400 metres of CSR trenching work 
  • bored a length of 45 metres which included underneath Creswick Lane 

Ongoing CSR works, crane mobilisation and deliveries of concrete will take place over the coming weeks and will require temporary road closures on Churchill Street. The Level Crossing Removal Project team will notify residents of any additional temporary road closures in advance via doorknocks and SMS. There will also be an increase in construction vehicles and machinery accessing and delivering project materials in the area. This work will be ongoing throughout 2022.

Upcoming night works: Surrey Hills and Mont Albert 

Between 9pm – 4am each night from Monday 2 May until Wednesday 4 May and also from Sunday 8 May until Wednesday 11 May, crews will work throughout night in the rail corridor and around Surrey Hills and Mont Albert Stations to deliver project materials. For further information please visit bigbuild.vic.gov.au.

What to expect 

Between 7am to 6pm on Tuesday 10 May intermittent road closures and traffic management will be in place on Churchill Street adjacent to Box Place to create a safe work zone while large concrete pits are delivered and lifted into site. Motorists can expect some minor delays while this work is carried out. 

The eastbound lane on Churchill Street (from the Mont Albert station and heading towards Elgar Road) is temporarily closed. Access to properties will be maintained via the westbound lane. 

The current arrangement will be in place until mid-2022 (day and night). Road users are advised to drive with care and follow the direction of traffic control and signage in place.

During this time:

  • Temporary road closures on Churchill Street, adjacent to Creswick Lane with traffic management in place 
  • Traffic management staff will be in place and some minor delays may be experienced while these works are carried out   
  • On-street parallel car parking on Churchill Street between the Mont Albert station entrance and Stanhope Street (station side) are now closed. 
  • Road traffic barriers and bollards are installed along Churchill Street to create a safe work zone  
  • On-street car parking along Churchill Street between Elgar Road and Stanhope Street is currently temporarily closed to enable traffic to be maintained in the westbound direction 
  • Access to driveways will be maintained, however some delays may be expected

Other impacts of these works include: 

  • Construction noise and activity, with vehicles, machinery and workers on site 
  • Minor delays for vehicles 
  • Traffic management to keep you and our workers safe 

The majority of work will take place during the day, 7am to 6pm Monday to Saturday. Please be aware that works can sometimes take longer than expected due to weather and other factors.

More information

You can now register to receive disruption information via text message. Simply text the word Churchill to 0459 067 028 to sign up to alerts for traffic and construction impacts for the Union Road and Mont Albert level crossing removal project.

For more information contact the Level Crossing Removal Project